Specification of 3phase 4wire CT operated trivector Energy meter
Sl No Description Technical specification and Display parameter
1 Application 3 phase 4wire, CT, PT operated
2 rated voltage -/230 (Phase to neutral)
3 rated current -/5 A( basic Current)
4 frequency 50± 5%
5 overload capacity 120% of Ib
6 Minimum starting currentin % of base current 0.1% of Ib
7 loss of potential circuit AS per IS: 14697:1999
  loss of current circuit AS per IS: 14697:1999
  Change in error due to AS per IS: 14697:1999
  a) variation in frequency AS per IS: 14697:1999
  b) variation in temparature AS per IS: 14697:1999
  c)variation in voltage AS per IS: 14697:1999
8 Accuracy class 0.5s
9 total weight of the case < 2kg
10 details of case Polycarbonate(seamless ultrasonic welding with transperent meter top cover)
11 HV withstand 4kv as per IS 14697:1999 cause 12.7.6.3
12 Insulation resistance As per 14697:1999
13 Standard to which the meter conferm AS per IS 14697:1999
14 Type of energy Registration mechanism Backlid LCD Display
15 MD Reset mechanism 1.Automatic on 24:00 hours of the last day of the month
2.manual Reset
16 Insulation test As per 14697:1999
17 Temparature co-efficient from 10% of rated load(5deg.C to 45deg.C) As per 14697:1999
18 Working range  
  voltage (-)50% to (+)20% of rated voltage
  current 0.1% to 120% of Ib
19 type of load(linear,non linear,balanced/unbalanced at any p.f) All types of load
20 Display Details(Descriptive in order of display) 1) Display test
    Real time and date
    Rising demand with elapsed time
    Active energy
    Reactive energy (both lag &lead)
    Apparent energy
    Maximum Demand(both KW & KVA)
    MD reset count
    Instantenuous power factor with sign for lag &lead
    Instantenuous frequency
    Instantenuous voltage (phase wise)
    Instantenuous current(phase wise)
    Instantenuous  Activeload
    Instantenuous reactive load (withsign for lag/lead)
    Instantenuous apparent load
    Billing power on hours
    TODenergies
    TOD Max demand in kva
    Cumulative max demand
    Present status of temper
    latest occurrence of Abnormality with date &time
    latest restoration of abnormality with date & time
21 ii)process of display(Automatic in cyclicmanner/through push botton
1)Automatic in cyclic manner(No 1,2,3,4,5,6,7,8,9) 2)through push botton
  iii) Digits 8(Eight) digits
  iv)Segments for display of one digit 7(seven)
  iv) period of display for each parameter 12(twelve) Seconds
22 Memory atnon volatile memory without battery back up at least 12 years
23 Non volatile memory Sufficient to store data(MD &energy) of consecutive12 biiling period in addition to tamper details7 TOD Zones,tamper information as described in detailed technical specification
24 meter can power up by means of external battery in absence of supply voltage meter can be powered up by means of internal battery in absence of supply voltage
25 tamper data preservation capacity Able to store at least 200 events(occurrence&restoration as separate events) with roll over facility
26 load survey capability  
  a) Parameter logged KW import,KVA
  b) Logging interval 15 minutes
  c)no of days load survey 70 days at interval of 15 minutes
27 earthing terminals AS per IS 14697:1999
28 Time of the zone zone-1- 7am to 10am
    zone-2- 10am to 18pm
    zone-3-18pm tp22pm
    zone-4-22pm to 6am
    zone -5- 6am to 7 am
29 capability for fraud prevention& detection
The meter stores in its memory occurrence and restoration the following tampers with date &time and also log of the event
    Missing potential
    CT short/Ct open
    CT short/Ct open
    Current unbalance
    Current missing
30 Sealing and locking arrangement 2 sealing screws on the meter cover& 2 sealing screw on terminal cover are provided.Separate sealing arrangement are provided for MD reset button& optical port
31 Type of communication Data can be transferred to and fro from aCmRI conforming to CBIP-111 through optical port conforming to IEC-1107 provided in front of the meter.data can also be transferred through central based computer using GSPMS lines and suitable modems.The data element size and its overhead speed of transmission should less than 10 minutes.
32 Others Meter should record energy correctly
    i) in case of Current reversal
    II)In case of neutral fail
    iii)In case of neutral disturbance
    iv) Meter should record at Imax in any tamper event due to magnatic influence
33 Real time Clock Time drift of Real time clock in the meteris less than±7 minutes per years
 
 
  North Eastern Electricity Supply Company of Orissa Ltd.
Corporate Office: At:Januganj, Balasore, Pin:756019,
Phone:(06782)-269864 Fax No:(06782)-263259
E-mail Id :nescoltd@hotmail.com ,
nescoltd@rediffmail.com, nesco@nescoorissa.com
Copyright © 2007 NESCO Powered By: Allasy Software Solution